17. Apply red (high strength) thread locking compound
to the wheel retaining bolt as shown. (fig. 13-26)
18. Install the bolt and tighten it. (fig. 13-27)
19. If you haven’t already, repeat steps 10-18 of this
procedure on the other side of the hub/wheel
assembly to secure the second wheel in place.
20. Once the hub/wheel assembly is together as
shown, torque the wheel retaining bolts to 180 ft.
lbs. / 244 Nm to secure them in place. (fig. 13-28)
21. Remove the allen plug from the center of the hub
assembly and fill it with 2 ounces of Terex 10W-30
Heavy Duty Engine Oil. Then reinstall the plug.
(fig. 13-29, 13-30)
22. Repeat this procedure on the other half of the
bogie assembly if necessary prior to installing the
two halves back onto the undercarriage.
23. Place the rubber rods back into position on the
square shaft, then tape them in place to keep
them secure while installing the bogie assemblies
around them. (fig. 13-31)
24. Reverse steps 1-3 of this procedure to reinstall the
bogie assembly back onto the undercarriage and
complete the procedure.
25. Repeat this procedure as necessary throughout
the PT-80 undercarriage to restore proper function.
13-7
Rubber Track Loader
13. Undercarriage
13-26
13-28
13-29
13-27
13-30
13-31